Shut San Onofre Nuclear Generating Station

Direct link to this page: https://copswiki.org/Common/ShutSanOnofre
Share Button

photo-Bumpersticker.jpg
Get Bumper Stickers!

Objective: Permanent decommissioning of San Onofre Nuclear Generating Station (SONGS)

WE WON! Southern California Edison announced a permanent shut down of the plant on Friday, June 7, 2013.

BUT THE BATTLE IS NOT OVER!! We are now working:

My goodness! Here's a list of all the media stories on San Onofre's closure!

Why was this plant a problem?

Please note, we are well aware that the plant continues to have very deadly nuclear material, some 1632 metric tons of high-level nuclear waste, in the form of spent and new nuclear fuel. Our battle continues to Decommission San Onofre and to establish a plan to manage the oversight of the decommissioning process and removal of the nuclear fuel. But the good news is that NO NEW WASTE is being generated!

earthquakemap.jpg
  • Puts 8.4 million residents at risk -- The San Onofre Nuclear plant puts approximately 8.4 million Californians at risk, given the same 50-mile evacuation area recommended for Americans near the Fukushima disaster. The 10-mile evacuation area is not reasonable given the stark realities of a full-scale accident such as happened at Fukushima, Chernobyl, and Three Mile Island.

  • Earthquake Risk Area -- California lies along the "ring of fire" of the Pacific Rim, where extreme earthquakes are common. San Onofre was originally designed to withstand a magnitude 6.0 earthquake, and then upgraded to withstand 7.0. However, we now know that earthquakes 100x stronger are possible, such as the 9.0 earthquake in Japan off the Fukushima Daiichi reactor, and a 7.4 quake hit near Mexicali. The Lake Wohlford dam "could crumble" in a 7.5 quake and so is being rebuilt to withstand a stronger quake. Recently, a magnitude 3.9 quake occurred along the San Joaquin Hills Thrust Fault on April 23, 2012, with epicenter within 15 miles of the plant. This fault was discovered 13 years ago, AFTER the initial licensing of the San Onofre plant, and it runs along the coast, very near the exact location of these reactors.

    Southern California Edison now proposes a $64 million seismic study to probe these recently discovered faults and somehow reassure everyone by saying the risks are not too great.

  • Tsumani Risk Area -- The 133 foot tsunami in Japan underscores the inadequacy of the 14 foot (over high tide) sea wall at San Onofre. Large sea waves can be caused by earthquakes, undersea landslides and even a random meteor strike. If any of these occurs, San Onofre could be disabled and enter uncontrolled meltdown.
steam1.jpg
  • Steam Generator Misdesign -- Four massive steam generators were replaced in a $670 million upgrade that was completed in 2010. In this project, SCE engineers worked to avoid NRC approval of the design changes to the steam generators. In the article written by the lead engineers on the project in Nuclear Engineering International which was published just before they started to fail, they said, "the major premise of the steam generator replacement project was that it would be implemented under the 10CFR50.59 rule, that is, without prior approval by the US Nuclear Regulatory Commission (USNRC)"

    It is now abundantly clear that the number and magnitude of the changes to the steam generators exceeded the intent of the like-for-like criteria. We can now clearly see that the underlying agenda of SCE, was to "improve" the steam generators so they would generate more steam and turn new generating turbines to push the limits of the plant to produce more power. Furthermore, the steam generators are very large reactor components that comprise a large fraction of the active elements within the containment structure, and were not originally intended to be replaced. These factors should have been enough to force NRC and public review during the design process. [See M 1252 to read this document.]

The changes to the steam generators were very significant, reviewed by nuclear expert Arnie Gunderson in this paper commissioned by Friends of the Earth.

It looks like the new steam generator design was intended to produce more steam, thus the reason for the replacement of the high-pressure turbines. See this article by the Orange County Register on the topic, prior to the emergency shutdown: M 1255

Later, for their non-compliance with the like-for-like "50.59" rule, SCE was cited by the NRC [See M 1406 to read the actual citation from the NRC.]

So that may be enough to show that the SCE was responsible for the failures, in that they chose to exceed the limits of the 50.59 like-for-like criteria, but it is worse than that.

It turns out that SCE was told by Mitsubishi Heavy Industries that fluid-elastic instability was a problem, and the Anti-vibration Bar team was told to ignore those warnings and proceed without any changes, because those changes would trigger a license amendment process. SCE's impropriety went beyond just stretching the limits of the 50.59 rule to avoid a license amendment process. They also knew the Replacement Steam Generators (RSGs) had vibration problems but did not correct them. This was first revealed in February, 2013, in this Los Angeles Times article See this later article where Boxer was ready to conduct a formal inquiry, just before the decision by SCE to permanently close the plant.

With this huge design mistake, how can we trust that the company can operate this plant safely? Humans always make mistakes, but even one mistake can be an irreversible disaster forcing many millions to evacuate.

  • Worst Safety-complaint Record -- workers at the plant have alerted NRC officials to more than 10x the national average of safety concerns. On April 20, a fire burned for 45 minutes and is still unexplained. Fire inspections that were supposed to be performed hourly were not done at all and logs knowingly altered for five years. The back up batteries, that need to be available within a single minute during an accident, were left disconnected for four years. A worker fell into the primary cooling pool at the plant on January 27, 2012, while trying to retrieve a flashlight, but the accident was "not technically a reportable incident under federal rules."

    worstsafetyrecord.jpg


Nuclear Power Myths

Myth 1. Nuclear Power is Carbon Free

"A life cycle analyses (LCA) carried out by Jan Willem Storm van Leeuwen and Philip Smith came to the following result: Electricity from atomic energy emits 90 to 140 g CO2 per kWh of electricity produced.

"The relatively high range of uncertainty is due to the different grade of ores used. It depends on how rich the ores are that are used to obtain the Uranium. For poor ores, the higher value does apply and for rich ores, the lower value does apply. This leads to an interesting issue: The world-wide reserves for Uranium are a very limited resource. It is estimated to last for about 50 to 70 years with the current demand. If additional nuclear reactors are built, the supply will last correspondingly shorter. The higher the demand for Uranium, the more and more poor ores will have to be processed. This however will lead to a CO2 balance for atomic power, which gets worse and worse over time.

"Storm and Smith in the above mentioned life cycle analysis came to the conclusion, that between the years 2050 (if additional nuclear power stations are built) and 2075 (no additional nuclear reactors) the CO2 emissions of electricity from atomic energy will be higher as the same electricity produced by a gas burning plant! So nuclear energy can definitely not be the solution to mitigate the effects of global warming!

"Let's compare the CO2 emissions to produce 1 kWh of electricity by different technologies:

Technology grams CO2 per kWh electricity
Solar power, water power and wind power 10 - 40
Nuclear power plants 90 - 140
Combined heat and power in private houses 220 - 250
Gas burning plants 330 - 360
New coal burning plants 1,000 - 1,100
http://timeforchange.org/co2-emission-nuclear-power-stations-electricity

Myth 2: Nuclear Power is Inexpensive

A. Consider the TRUE cost of nuclear power -- "The efforts to consolidate the radioactive waste of one nuclear power plant in a safe manner will require investments of energy, materials and economic power of the same order of magnitude as the investments during the operational lifetime of the reactor. After closedown of a nuclear power plants, a massive energy debt is left to society, increasing over time due to the unavoidable deterioration of the temporary storage facilities and increasing leaks.

"This debt cannot be written off as incollectable, like a financial debt, because the health of millions of people is at stake. If it goes wrong with the radioactive heritage of a nuclear power plant - and it will go wrong if nothing is done - it will go terribly wrong. We just cannot move millions of people to another, not contaminated region. Obviously the economy will also suffer a heavy setback in case of a severe accident. The chance of such accidents increase with time.

"Nuclear power delivers energy on credit." http://www.stormsmith.nl/i16.html

B. Non-nuke power district rates are lower -- Whenever SoCal Edison/San Onofre boosters talk about how they need their electricity rates to "stay low", point out the TRUE rates being paid by SoCal Edison customers compared to others in California. SoCal Edison's electricity rates (with 80% ownership of San Onofre) are 50% higher than those of L.A. Dept. of Water and Power (which owns less than 7% of Palo Verde Nuclear Power Plant) and Sacramento Municipal Utility District (which decommissioned Rancho Seco over 20 years ago after a public referendum).

http://sanonofresafety.files.wordpress.com/2011/11/compareyourelectricrates2012-04.pdf

Myth 3: Nuclear Energy is Reliable

With the San Onofre plant down for over a year, this is hardly a poster-child for reliability. But even without these design mistakes, the grid operator must be aware that all nuclear plants MUST be taken off line for weeks or months at a time to allow for refueling. During these periods, there must be adequate capacity elsewhere to make up for these down periods. So by definition, nuclear power is not always reliably available.

Nuclear power boosters say, "Replacing nuclear power means increasing CO2 emissions and solar/wind is intermittent." But the TRUE state of the current energy marketplace, which is a DISTRIBUTED generation near the point of use, provides for far greater reliability and efficiency.

  1. Fuel Cells: "Fuel cells are fundamentally more efficient than combustion systems, achieving 40% to more than 50% fuel-to-electricity efficiency when using hydrocarbon fuels such as natural gas or pure hydrogen, depending on the type of fuel cell and the application. High efficiency is an inherent advantage for fuel cells because they use the chemical energy of a fuel directly, without combustion. Hybrids, such as systems that combine high temperature fuel cells with a turbine, can operate at electrical efficiencies estimated at more than 60%, higher than even the most efficient combined cycle turbine plants now available.

    "When the fuel cell is sited near the point of use, waste heat can be captured for cogeneration, where it can be used to provide hot water, space heating, or cooling. This combined heat and power (CHP) installation can deliver 80% to 90% overall fuel efficiency. Heat can also be used for refrigeration using absorption chillers, as supermarkets installing fuel cells are opting to do. In buildings, fuel cell cogeneration units can reduce facility energy service costs by 20% to 40% compared to conventional energy technologies."

    http://www.fuelcells.org/wp-content/uploads/2012/02/BusinessCaseforFuelCells.pdf
  2. Solar Rooftops: As of the Summer of 2012, the CA Public Utilities Commission reported that California is generating 1,255 MW of electricity from 122,516 rooftops (more than one of the San Onofre Units). Rooftop solar installation can be done in a matter of months, not the years that power plant construction requires. The CA Air Resources Board estimated in June 2010 that 150 permanent jobs are created for each 100 megawatt (MW) of local solar added. As an indication of the growth potential of this job sector, in San Diego County, we have only installed 2% (or 140 MW) of rooftop and parking lot capacity -- this is a GROWTH industry!
  3. "Intermittent" Solar and Wind Power: Southern California experiences about 290 days of sunshine per year, and "peak use" of electricity occurs from 10 am to 6 pm, which happens to be the peak time for sunshine, too (noting November-February shorter daylight, also lower electricity demand) . Wind tends to rise overnight, which complements solar's daytime production, as well as during stormy weather. A microcosm of this symbiotic relationship can be found in a suburban tract home in Oceanside, CA (north San Diego County), which is nearing 1 Year completely off the grid, using solar rooftop to charge batteries during the day, a micro-wind turbine to charge batteries overnight, and energy efficient appliances.
  4. Re-THINK Not Re-Start: We need to update our electricity grid to reflect the innovations in electricity production, which are DISTRIBUTED, not centralized. Electrical engineers know how to do this, and THIS should be a focus of our technological innovation, NOT making our future fit the constraints of the archaic technologies of the 20th Century. For example, from the trade journal Power Engineering: "Converting an obsolete synchronous generator to a synchronous condenser is a viable, economical alternative to retiring the unit. As the condenser is a rotating device, it can also provide short circuit support in addition to reactive power capacity. While converting the unit requires a system-level approach and custom engineering, the result can greatly extend the generator’s useful lifespan. For the community, a conversion to a synchronous condenser can provide electrical system voltage support resulting in a stable source of electric power."

    ttp://www.ge-energy.com/content/multimedia/_files/downloads/Converting_Existing_Synchronous_Generators_into_Synchronous_Condensers.pdf

Sub-projects

Topic Description Status Parents
A 29 San Onofre Protest And Rally Three Mile Island! Chernobyl! Fukushima! San Onofre? Shut Down San Onofre Closed Shut San Onofre
Coalition To Decommission San Onofre Grassroots organizations joined as a party to the California PUC Inactive Shut San Onofre
M 11 San Onofre Protest And Rally Rally/Protest on First Anniversary of Fukushima disaster at San Onofre Nuclear generating Station (SONGS) Closed Shut San Onofre
San Onofre License Amendment Intervention Processing of Petition to Intervene and Request for Hearing regarding License Amendment Request for San Onofre Closed Shut San Onofre
San Onofre Settlement Federal Case Complaint by Citizens Oversight et al vs. CPUC on San Onofre Settlement Inactive Shut San Onofre, Stop The Unfair Settlement
Stop Nuke Dump Move the San Onofre waste to a better location (& Pendleton Option) Hot Shut San Onofre
Stop The Unfair Settlement The utilities are pushing for a quick $3.3B settlement that is unfair to ratepayers Inactive Shut San Onofre

Latest News: Upcoming meetings and events

  • 13 Jun 2012 - (6p) Join with other Shut San Onofre activists at Encinitas City Council Meeting, Encinitas City Council Chambers 505 S. Vulcan Avenue, Encinitas 92024
  • 18 Jun 2012 - (5p) NRC Report on San Onofre Nuclear Generating Station regarding findings from their investigation and reponse from Edison officials, at San Juan Capistrano Community Center 25925 Camino Del Avion, San Juan Capistrano, CA 92675. Please arrive by 5pm for protests and events prior to the meeting which starts at 6pm.
  • 20 Jun 2012 - (2p) Meeting with representatives from the San Diego "Public Safety and Neighborhood Services Committee" in an effort to get this on the agenda.
  • 18 Jul 2012 - (2p) San Diego "Public Safety and Neighborhood Services Committee" at San Diego City Council Committee Room (12th Floor, San Diego City Administration Building) - Public comment limited to 3 minutes per topic, but we may be on the agenda.
  • 24 Sep 2012 - (6p) Del Mar City Council Meeting FB Event Southern California Edison will be giving a 20 minute presentation; Daniel Hirsch will be present to give a 20 minute rebuttal/presentation on the dangers of reopening San Onofre. Please plan to attend this important meeting and show Del Mar that we want San Onofre to stay shut! 1050 Camino del Mar, Del Mar, CA 92014.
  • 29 Sep 2012 - (10a-2p) Politifest at Ingram Plaza in Liberty Station, see Website for details. Will have a booth there to promote shut down.
  • 09 Oct 2012 - (6-9:30p) NRC Public Meeting on San Onofre at St Regis Hotel Dana Point at 1 Monarch Beach Resort North, Dana Point, CA 92629. This is a Category 3 Meeting, and the first time local concerned citizens, the NRC, and Southern California Edison wil take part together in a roundtable discussion about San Onofre Nuclear Generating Station.
  • 25 Oct 2012 - (9a) CPUC meeting includes an agenda item to open an investigation into San Onofre. At Irvine City Hall, Council Chambers, 1 Civic Center Plaza, Irvine, CA 92606
  • 30 Oct 2012 - (4:30-7:30p) Southern California Edison is sponsoring a San Onofre informational meeting, Vista Civic Center, Morris B. Vance Community Room, 200 Civic Center Drive. Activists plan to be there to provide the other side of the story.
  • 16 Nov 2012 - (6-9p) NRC will meet with Southern California Edison (SCE) to discuss SCE's response to the NRC Confirmatory Action Letter of March 27, 2012, concerning actions required to be taken to address steam generator tube degradation at San Onofre Nuclear Generating Station. At Doubletree Doheny Beach at 34402 Pacific Coast Highway, Dana Point, CA 92629. Seating is limited to 350. See meeting notice -- THIS MEETING HAS BEEN INDEFINITELY POSTPONED Project: Shut San Onofre.
  • 30 Nov 2012 - (4p) Press Conference by Coalition to Decommission San Onofre. Outside The Hills Hotel at 25205 La Paz Rd, Laguna Hills CA. Project: Shut San Onofre.
  • 30 Nov 2012 - (6-9p) NRC will meet with Southern California Edison (SCE) to discuss SCE's response to the NRC Confirmatory Action Letter of March 27, 2012, concerning actions required to be taken to address steam generator tube degradation at San Onofre Nuclear Generating Station. At The Hills Hotel at 25205 La Paz Rd, Laguna Hills CA. Seating is limited to 400. Project: Shut San Onofre.
  • 13 May 2013 - 17 May 2013 - CPUC holds hearings on San Onofre. This is Phase 1, regarding the reasonableness of SCE's actions after the shutdown and the information provided to the public. Location is the California Public Utilities Commission headquarters in San Francisco.
  • 07 Jun 2013 - Press conference at San Onofre to celebrate the announcement by SCE that the plant will be permanently closed! From San Onofre License Amendment Intervention

  • 05 Dec 2012 - (10a PST) Pre-hearing proceeding on San Onofre License Amendment Intervention. Atomic Safety and Licensing Board Panel’s Rockville Hearing Room, located on the third floor of Two White Flint North, 11555 Rockville Pike, Rockville, Maryland. For the benefit of the public, the proceeding will be webcast at http://www.visualwebcaster.com/event.asp?id=91000. Ray Lutz will be participating by video conference at a location in San Diego with unfortunately no room for the public. Meeting length less than three hours. We are working to set up a public viewing location, likely at the World Resources Simulation Center, where we will have a press conference at 9am prior to the meeting and Ray Lutz will rejoin the public for a debriefing after the proceedings.
  • 05 Dec 2013 - NRC Commission ruled that since plant is now close, appeal of ASLB ruling was now moot. Ruling of ASLB vacated, appeal dropped. See document list for NRC ruling.

Background

  • 2,200-megawatt power plant in the northwest corner of San Diego County
  • Each reactor can generate 1,100 megawatts of electricity when operating at full power, enough to supply 1.4 million households.
  • Southern California Edison owns 78 percent of the plant, San Diego Gas & Electric 20 percent and the city of Riverside 2 percent.
  • Each reactor has two steam generators, each with 9,727 tubes.
  • Licenses for Units 2 and 3 expire in 2022 and '23

Timeline

Date Description
1980-04-08 SONGS Unit 1 steam generator leak discovered.
1982-02-16 Unit 2 Licensed. Details
1982-11-15 Unit 3 Licensed. Details
1982-12-13 CPUC again deferred decision on whether SCE could recover costs associated with Unit 1 steam generator repairs. The Commission permitted a four-year amortization of the repair costs, beginning in test year 1983, with only the last three years (about $53 million) subject to refund. The Commission noted that Westinghouse, not SCE, bore responsibility for the faulty design of the tubes and that the record contained “no basis . . . to conclude that Edison acted unreasonably in accepting what proved to be a faulty plant design or in its detection and repair of the steam generator failure.” D. 82-12-055, 10 CPUC 2d 155, 1982 WL 196701, at *31 (1982).
1983-03-31 SCE filed suit against Westinghouse regarding steam generator tube failures in Unit 1.
1983-10-05 The CPUC issued I.83-10-02, which began the investigation into whether the Commission should disallow rate recovery of the Unit 1 repair costs.
1984-04 SONGS Unit 3 started commercial operation at nominal 100% power with new Combustion Engineering (CE) Steam Generators.
1986-09-04 after a full factual investigation and hearing, and after conclusion of the litigation between SCE and Westinghouse, the CPUC determined that SCE had imprudently executed a release of liability that prevented SCE from recouping its costs from Westinghouse through litigation. Only at that point did the Commission order SCE to refund 75% of the repair costs to ratepayers. See D. 86-09-008, 22 CPUC 2d 14 (1986).
2004-09-30 SCE signed a contract with Mitsubishi Heavy Industries, America, for fabrication of replacement steam generators (prior to approval of the project by the CPUC).
2005-12-15 CPUC Decision approving SGRP (D.05-12-040)
2009-01-10 Two replacement generators, manufactured by Mitsubishi Heavy Industries, arrived in Del Mar Basin in Camp Pendleton.
2009-12 NRC reported that the plant's staff didn't notice that a backup battery for safety systems was inoperable between 2004 and 2008.
2010-10-10 Unit 3 started the Cycle 16 Refueling and Steam Generator Replacement Outage. The original CE SGs (3E088 and 3E089) were replaced with MHI SGs.
2011-02-18 Unit 3 completed the Cycle 16 Refueling and Steam Generator Replacement Outage and returned to operation at nominal 100% reactor power.
2012-01 Southern California Edison engineers publish an article in the Nuclear Engineering International that describes the numerous changes that were made to the steam generators, and said the major premise of the project was to avoid NRC approval, and that they were not even sure they would perform to spec given the many changes that were made, including the addition of 370 tubes in each steam generator. An article in the Orange County Register said the steam generators raised the amount of steam generated. These actions together likely comprise an illegal increase in reactor power capacity without the legally required license amendment.
2012-01-09 U2 Cycle 17 refueling outage (RFO) start: SCE removed Unit 2 from service for the planned Unit 2 Cycle 17 refueling outage 2012, and to install a new turbine with increased power output, enough to power 31,000 homes.
2012-01-27 Worker falls into primary coolant pool trying to reach his flashlight. Edison said the event did not qualify for reporting because he did not receive a high enough dose of radiation.
2012-01-27 U2 fuel moved from fuel pool completed
2012-01-31 San Onofre Unit 3 shut down after a leak that may have released a small amount of radioactive gas was found in a steam-generator tube. Leak rate was about 75 gallons per day.
2012-01-31 15:05 Unit 3 Operators entered Abnormal Operation Instruction (AOI) SO23-13-14 (Reactor Coolant Leak) which was required for a primary-to-secondary SG tube leak exceeding 5 gallons per day.
2012-01-31 16:10 Operators commenced AOI SO23-13-28 (Rapid Power Reduction) for a leak rate greater than 75 gallons per day with an increasing rate of leakage exceeding 30 gallons per hour.
2012-01-31 17:31 Operators manually tripped the reactor from 35% power.
2012-01-31 17:38 Operators entered Emergency Operating Instruction (EOI) SO23-12-4 (Steam Generator Tube Rupture).
2012-01-31 18:00 Operators isolated the affected SG.
2012-02-02 Unit 3 Reached cold shutdown conditions.
2012-02-05 U2 steam generator retainer bar problem identified
2012-02-08 Senator Barbara Boxer (D-CA), Chair of the Environment and Public Works Committee, sent a letter to the Chairman of the Nuclear Regulatory Commission (NRC), Dr. Gregory Jaczko, requesting that the NRC review and report on the safety conditions at the San Onofre nuclear plant due to the recently discovered problems related to tubes that carry radioactive water at the facility. Senator Boxer asked the NRC to assess the conditions at the plant, which is located in San Clemente, California, to determine if further action is needed.
2012-02-11 U2 initial Eddy Current Testing (ECT) completed
2012-02-12 U3 ECT inspection locates leaking tube
2012-02-12 Started tube inspections, one tube found with small leak. Proceeded with expanded eddy current inspection of 100% of the tubes, finding 129 tubes requiring in-situ pressure testing.
2012-02-13 Pressure testing resulted in three tubes failing.
2012-02-14 U2 expanded ECT (based on U3 findings) completed
2012-02-14 U2 Replace Emergency Core Cooling System mini flow piping project completed
2012-03-01 U2 fuel move to core from fuel pool completed
2012-03-02 U2 High Pressure Turbine retrofit project completed
2012-03-04 U2 Replacement Reactor Vessel Head project completed
2012-03-04 U 2 C 17 RFO originally scheduled to end (Return To Service - RTS)
2012-03-11 "Fukushima Remembered" Rally at the San Onofre plant to push to close the plant and commemorate the ongoing disaster at the Fukushima Daiichi reactor. See Video See this page for all media and press coverage: M 11 San Onofre Protest and Rally
2012-03-13 Chairman Jaczko responded, “The root cause of the tube leak has not yet been determined. …NRC approval is not required for the licensee [Edison] to restart Units 2 and 3.”
2012-03-13 U 2 C 17 RFO schedule slip from 3/20 to 4/15 due to additional ECT
2012-03-13 U3 In-situ pressure test of 129 tubes. 8 tubes fail.
2012-03-14 U 2 C 17 RFO schedule slip from 4/15 to 5/16
2012-03-16 U2 equipment hatch closed
2012-03-19 NRC begins onsite Augmented Inspection Team
2012-03-23 SCE submits Steam Generator Return-to-Service Action Plan to NRC
2012-03-27 U 2 C 17 RFO schedule slip from 5/16 to 6/1
2012-03-27 Confirmatory Action Letter issued by NRC
2012-03-27 Arnie Gundersen of Fairwinds Associates published a review of the steam generator failures and pointed to the numerous design changes as the likely root cause. He said "San Onofre engineers should have precise maps detailing the degraded and leaking tubes as well as the exact location of the leak(s) in each tube. Such data is just one piece of critical information required in conducting a thorough root cause analysis of the problem and determining an accurate solution."
2012-03-27 NRC issued a "Confirmatory Action Letter says SONGS to remain shut down until all problems are understood and are resolved.
2012-03-27 Irvine City Council starts the process to formally request that SONGS be permanently decommissioned.
2012-04-01 U2 FAC project completed
2012-04-02 U2 RTS scheduled for 6/1/12
2012-04-03 U2 equipment hatch opened
2012-04-04 NRC Chair Gregory Jaczko toured the plant and said it will continue to be shut down. Radio Story
2012-04-06 Community members met with NRC chairman Gregory Jaczko at Doubletree Hotel in Dana Point
2012-04-06 U2 special interest ECT
2012-04-15 U3 initial ECT completed
2012-04-20 U2 TTW inspection letter to NRC
2012-04-20 45 minute fire at turbine side of Unit 2
2012-04-23 3.9 Magnitude earthquake along San Joaquin Hills Thrust Fault with epicenter within 15 miles of the plant
2012-04-23 U2 first tube wear root cause analysis issued by SCE
2012-04-23 U2 Emergency diesel generator replacement project completed
2012-04-24 U2 tube plugging and stabilizing list issued
2012-04-25 Citizens Oversight sends a letter to the NRC requesting specific steps be taken before a reactor restart, and Announces the April 29 rally to the media.
2012-04-29 2nd Rally at the power plant, to commemorate the 33 year anniversary of Three Mile Island, 26-year anniversary of the Chernobyl disaster, and the ongoing Fukushima meltdown of 3 reactor cores with 7 additional nuclear cores in unstable fuel pools. See Video
2012-05-07 U 2 C 17 RFO schedule slip from 6/1 to 7/1
2012-05-07 U3 first tube wear root cause analysis issued by SCE
2012-05-16 NRC Memo on Inspection Charter for Augmented Inspection Team (AIT). It says "It is not the responsibility of the team to examine the regulatory process." On site inspections were to be complete by March 30. (Strange that the memo was dated May 16). This is just a revision of the earlier document stating to include assessment of "licensee actions taken in response to the Confirmatory Action Letter."
2012-06-18 Friends of the Earth hold a press conference just prior to the NRC meeting disclosing that they are filing a petition to become an intervenor and demand a hearing on the actions of Edison to avoid NRC approvals in their steam generator project. See Full Video; Short Video by Ace Hoffman
2012-06-18 NRC Report on San Onofre Nuclear Generating Station regarding findings from their investigation and response from Edison officials. See Video. They said the cause of the unusual tube-to-tube wear was due to excessive steam velocity, but did not follow up and come to the conclusion that the steam velocity was caused by the design changes. (Full Transcript of this meeting available).
2012-07 Efforts began to place the Unit 3 primary and secondary systems not required to be operable or in service into a preservation mode. A comprehensive preservation plan was developed and implemented in order to minimize corrosion and other equipment degradation mechanisms. This plan consists of approximately 50 actions required to lay-up and preserve systems not currently required to be in service or available and is currently being implemented.
2012-09-22 Workplace safety audit (Q of ALJ MD.)
2012-10-03 SCE submitted a restart plan to the Nuclear Regulatory Commission (NRC) for approval to restart Unit 2 at 70% power and with scheduled mid-cycle outage inspections following 5 months of operation.
2012-10-13 CPUC orders instituting investigation (OII) into the rates being charged by SCE and SDGE regarding SONGS. (I.12-10-013)
2012-11-01 "Issuance Date of the OII"
2012-12-10 CPUC General Rate Case (GRC) decision (D.12-11-051) set the 2012 annual revenue requirement associated with SONGS 2&3 at approximately $498 million (excluding SGRP, ERRA and NDCTP).
Required the establishment of SONGSMA to track expenses and reductions so that the CPUC could possibly remove some of these costs from the rate base.
Required that SCE file an application for a reasonableness review of the expenses tracked by SONGSMA (Consolidated with OII).
2012-12-12 SCE submitted testimony regarding proposed rate adjustments for SONGS units 2 & 3. See M 1352 for details on this testimony.
2013-04-16 SCE Submits a request for license amendment to operate Unit 2 at 70% power. Fed. Register Entry
2013-06-07 SCE announces permanent closure of SONGS
2005 Hearings on steam generator replacement project (SGRP).
2007 SCE began preliminary engineering of a new High-Pressure Turbine (HPT) for delivery in 2011. "This retrofit also will take advantage of the increased steam pressure following replacement of the SONGS Steam Generators. See D.05-12-040" (SGRP). This quote from footnote 10 of "SCE-02: Generation, volume 5 - SONGS 2 & 3 HPT Project"
2009 Unit 2 Steam Generator replaced by cutting 28 ft hole in the containment structure (concrete 4-6 ft thick)

Images

%IMAGEGALLERY{titles="off" columns="6" warn="off"}% (Just attach your images to this topic and they will automatically be added to the gallery above!)

Stress Testing

Japan and the EU has embarked on a process to stress test reactors, subjecting them to extreme conditions without regard the likelihood that such events may occur.

Summary of articles submitted (Add | All):

Number of topics: 297

Discussion List

See List Serve for all email discussion lists and to add more.

List Title
(Name)
Description Project Who may subscribe? Who May Post Info
Admin
Shut San Onofre List
(shutsanonofre)
Discussion and Announcements for Shut San Onofre Project Shut San Onofre Anyone
Subscribe
Admins
Post
Info Archive Admin
Shut San Onofre WG
(shutsanonofrewg)
Discussion of working group on Shut San Onofre Shut San Onofre Anyone
Subscribe
Anyone
Post
Info Archive Admin
Songs Oii List
(Songs OII Service List)
List of official recipients of filings to CPUC proceeding I.12-10-013 Shut San Onofre You must be a party or service list subscirber.
Subscribe
Only COPS official filers
Post
Info Archive Admin

Project Form edit

Project Name Shut San Onofre Nuclear Generating Station
Project Description Objective is permanent decommissioning of SONGS
Project Founder Ray Lutz
Project Curator Ray Lutz
Project Type Issue Oversight
Project Parents Nuclear Energy
Related Keywords California Public Utilities Commission, Coalition To Decommission San Onofre, Nuclear Energy, Nuclear Waste, Shutdown Diablo, Shut San Onofre, Stop The Unfair Settlement
Project Status Active
Thumbnail Link screamlogo100x100.jpg
Forum Link
List Serve Topic
I Attachment Action Size Date Who Comment
003.jpgjpg 003.jpg manage 106 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
004.jpgjpg 004.jpg manage 62 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
007.jpgjpg 007.jpg manage 60 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
012.jpgjpg 012.jpg manage 129 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
016.jpgjpg 016.jpg manage 125 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
019.jpgjpg 019.jpg manage 108 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
020.jpgjpg 020.jpg manage 141 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
021_(1).jpgjpg 021_(1).jpg manage 55 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
023.jpgjpg 023.jpg manage 67 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
025.jpgjpg 025.jpg manage 114 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
026.jpgjpg 026.jpg manage 131 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
033.jpgjpg 033.jpg manage 129 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
034.jpgjpg 034.jpg manage 162 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
035.jpgjpg 035.jpg manage 108 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
036.jpgjpg 036.jpg manage 121 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
038.jpgjpg 038.jpg manage 107 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
041.jpgjpg 041.jpg manage 63 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
042.jpgjpg 042.jpg manage 118 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
0429121316.jpgjpg 0429121316.jpg manage 1 MB 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
0429121316a.jpgjpg 0429121316a.jpg manage 838 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
0429121316b.jpgjpg 0429121316b.jpg manage 1 MB 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
0429121316c.jpgjpg 0429121316c.jpg manage 1 MB 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
044.jpgjpg 044.jpg manage 93 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
046.jpgjpg 046.jpg manage 107 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
047_(1).jpgjpg 047_(1).jpg manage 138 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
048.jpgjpg 048.jpg manage 125 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
049.jpgjpg 049.jpg manage 126 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
050.jpgjpg 050.jpg manage 115 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
054.jpgjpg 054.jpg manage 150 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
056.jpgjpg 056.jpg manage 114 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
058.jpgjpg 058.jpg manage 114 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
2-San-onofre.jpgjpg 2-San-onofre.jpg manage 68 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
36268_fca3b4b0642563cd4ef3236aee3b0597_f6d24890d2a2311030ab0ded5ca1c086.jpgjpg 36268_fca3b4b0642563cd4ef3236aee3b0597_f6d24890d2a2311030ab0ded5ca1c086.jpg manage 46 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
36269_84463ce973053da096658f832c412e26_a5ca7206a49fec1dba5be9e2bdc33f48.jpgjpg 36269_84463ce973053da096658f832c412e26_a5ca7206a49fec1dba5be9e2bdc33f48.jpg manage 41 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
4fd968d5680de.preview-620.jpgjpg 4fd968d5680de.preview-620.jpg manage 90 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
6a00d8341c630a53ef017c32b8ffec970b-640wi.jpgjpg 6a00d8341c630a53ef017c32b8ffec970b-640wi.jpg manage 110 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
Chrystal_Coleman_from_Vista_0.jpgjpg Chrystal_Coleman_from_Vista_0.jpg manage 20 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
DSC_0014.jpgjpg DSC_0014.jpg manage 91 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
Image.jpgjpg Image.jpg manage 404 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
SanOnofreSiteOverview.jpgjpg SanOnofreSiteOverview.jpg manage 119 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
ShutDownPressConf.jpgjpg ShutDownPressConf.jpg manage 69 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
ShutSONGS_Logo75.pngpng ShutSONGS_Logo75.png manage 28 K 26 Jun 2014 - 21:22 Raymond Lutz  
TooCloseToTheOceanInfographic.JPGJPG TooCloseToTheOceanInfographic.JPG manage 71 K 10 Sep 2015 - 19:53 Raymond Lutz Too Close to the ocean -- infographic
earthquakemap.jpgjpg earthquakemap.jpg manage 298 K 26 Jun 2014 - 21:22 Raymond Lutz Fault lines and evacuation area near San Onofre
la-174638-me-1009-sanonofre-8-ajs.jpg-20121009.jpgjpg la-174638-me-1009-sanonofre-8-ajs.jpg-20121009.jpg manage 71 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
sano-photo-nrcwebsite.jpgjpg sano-photo-nrcwebsite.jpg manage 23 K 26 Jun 2014 - 21:22 Raymond Lutz San Onofre Nuclear Generating Station
screamdone.jpgjpg screamdone.jpg manage 19 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
steam1.jpgjpg steam1.jpg manage 26 K 26 Jun 2014 - 21:22 Raymond Lutz Steam Generator
victory_hug_1.jpegjpeg victory_hug_1.jpeg manage 27 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
weshutsanonofre.jpgjpg weshutsanonofre.jpg manage 18 K 07 May 2015 - 21:45 Raymond Lutz Submitted by e-mail
worstsafetyrecord.jpgjpg worstsafetyrecord.jpg manage 176 K 26 Jun 2014 - 21:22 Raymond Lutz San Onofre has the worst safety record in the nation
Topic revision: r57 - 08 Apr 2024, RaymondLutz
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding Cops? Send feedback